Governor Cuomo Announces New Reforms Designed to Keep State Highway Construction Projects on Budget and on Time

[1]


Albany, NY (November 16, 2011)

Cabinet Meeting Presentation [2]

 

Governor Andrew M. Cuomo today announced new reforms designed to keep state highway construction projects on budget and on time.

 

These changes come after a series of recommendations from an independent review, ordered by the Governor, of delays and cost over-runs which have affected I-287 in Westchester for over a decade. 

 

"I have repeatedly said that government must protect every taxpayer dollar by being efficient and effective," Governor Cuomo said. "For over a decade, the I-287 project has been mired in delays and cost over-runs, and that's why I ordered an independent review and that's why the Department of Transportation is making these important reforms."

 

The I-287 Cross Westchester Expressway Corridor project began 15 years ago. The original cost of the first five stages was expected to be $490 million, but ended up being $568 million, as overruns drove the price up by 16%.

 

In June, Governor Cuomo ordered an independent and comprehensive review of the I-287 project in response to the significant, unexpected costs and delays. Peter Lehrer, a renowned national construction expert, led the review. Lehrer's work includes the restorations of the Statue of Liberty, Ellis Island, Grand Central Terminal, and the American Museum of Natural History.

 

The review team conducted two months of interviews with NYS Department of Transportation (DOT) management staff, contractors and construction experts. The team also reviewed project metrics, project cost and schedule data, contracts, change orders and bid documents. They also conducted research on best practices within DOT and other states. 

 

The key problems identified by the review include: 

 

The review called for two categories of reforms: one for project management and one for agency-wide reform within the Department of Transportation.

 

Regarding project management, steps DOT has taken include:

 

Regarding agency-wide changes, steps DOT has taken include: 

 

DOT has consistently had overruns on its projects in the 7% to 11% range, resulting in $530 million in total overruns over the past five years. Best-in-class state DOTs have achieved cost overruns that are less than 5% of their capital program. In addition to overruns, nearly half of DOT projects are delayed, with average delays of over six months. During the last seven years, projects over $25 million have been an average of 306 days late. Best-in-class DOTs deliver 80% to 90% of their projects on-time.

 

With this new approach to project and agency operations and management, DOT has issued new program goals including 90% of projects delivered on-time and no more than 5% overruns for all projects. As a result of the revamped approach to state construction, the I-287 project will be substantially completed by December 2012 instead of August 2013. 

 

Joan McDonald, Commissioner of the New York State Department of Transportation, said, "Since taking office, Governor Cuomo has made it a priority to make government work more efficiently for the taxpayer and today is another step in this direction. As a result of these recommendations, DOT is transforming the way we manage construction projects across the state, while also making important changes within the agency. As we strengthen New York's infrastructure and build new highways and roads across our state, we must continue to do all we can to make sure projects are managed efficiently and completed on time."

 

Peter Lehrer said, "While our state and country continues to find ways to fund much needed infrastructure projects, we cannot forget the importance of spending the limited dollars that we do have in an efficient manner. Although the work on I-287 has created a better highway for the residents of Westchester, our infrastructure dollars could have been spent more wisely. I am pleased that Governor Cuomo tasked me with undertaking a comprehensive review of this project, and I believe our findings and recommendations will help transform DOT into a stronger, more efficient organization that will save taxpayer dollars while building and strengthening New York's infrastructure."